Monday, July 19th, 2010 | by admin
Hwy 281 SuperStreet – Project status
The MPO approved funding for this project on March 23rd, 2009. Funding is coming from a combination of funds from the federal stimulus, Advanced Transportation District, and City of San Antonio.
On January 14th, ARMA’s board selected Ballenger Construction’s bid of $5.2 million to build the project.
Ground was broken on the project on March 11th and should be completed by late September. Nearly all work is being done at night to minimize disruptions to traffic. As of early July, the work was about 40% complete, with some delays due to unusually wet weather this Spring.